Blankpage
alien
All together there was 17 Bents/Footing that were on the project (for the bridge). There were 8 piles per footing, IIRC. The piles were always part of the contract. Kiewit was the GC and they initially began to drill the piles using their reverse oscillation method. Basically, it's an open hole method that works good in competent material (they actually did a few Bents with this method). But when they got to the deeper shafts, and the claystone/siltstone turned to weathered crap, they couldn't keep the hole open and had caving conditions. So they had to backfill the shafts and come up with a new game plan.
So after wasting alot of time and money. Caltrans pretty much said that the shafts had to be cased down to tip. Being that Malcolm was the only driller with the equipment capable to do such a job, they made a lot of money. It was all T&M...I think it was around a $40M dollar job. It was a pretty impressive job.
The 3 Bents you may be thinking of might have been the land footings, which Malcolm did on the south side, I believe in early 2002...prior to me coming on board.
Yes pile were always part of the design but rotating them into place was not. Kiewit had a pile hammer that happened to be the biggest one on the west coast until they bought a bigger one for the Bay Bridge pile.
Initially the Benicia pile driving was killing fish from the high decibel level travelling through the water, measured at near 200 decibels in the water. So a bubble curtain was configured around the pile during pile driving by placing large compressors on barges and blowing compressed air through perforated pipes around the pile. This was allowed only twice a day at slack tide instead of driving pile for full shift as was initially planned. This added over a year to the project.
There were 8 pile per footing except for piers 7 and 8 which were on either side of the navigation span. Those two had 9 pile. At pier 7 the sub soil was harder than expected from the soil samples. If you remember some of the pile at pier 7 were already driven by the time Malcolm showed up and were sticking well above their design elevation. They had to be water jet cut and a platform built over those pile for Malcolm to place their rotator.
At pier 8 it was the opposite, the soil was softer than expected and the cave in issues. Malcolm also drilled the pile on the north shore at pier 16.
Pier 9 was the first pier to have its pile driven and was finished before Malcolm came onto the project. The cost to the project in delayed schedule, Malcolm, supporting Malcolm with platforms, pile cutting… was over $100M.
The initial contract was won by Kiewit with a bid of around $278M. The total paid to Kiewit in the end was over $800M.
Last edited:

